NOTICES: Electric rate and corporate regulation combined filings,
Published: 2007-12-18
December 12, 2007.
Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings:
Docket Numbers: RP99301173.
Applicants: ANR Pipeline Company.
Description: ANR Pipeline Company submits amendment to two Rate
Schedule FSS and ETS negotiated rate agreements with Wisconsin Gas LLC,
to be
NOTICES: Electric rate and corporate regulation combined filings,
Published: 2007-12-18
December 11, 2007.
Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings:
Docket Numbers: RP05157008.
Applicants: Saltville Gas Storage Company, LLC.
Description: Saltville Gas Storage Company, LLC submits Original
Sheet 20 et al. to FERC Gas Tariff, Original Volume 1, to become
NOTICES: El Paso Natural Gas Pipeline Co.,
Published: 2007-12-18
December 11, 2007.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Hobbs Expansion Project
involving construction and operation of natural gas pipeline facilities
by El Paso Natural Gas Pipeline Company (El Paso) in Lea
NOTICES: Leaf River Energy Center LLC,
Published: 2007-12-18
December 11, 2007.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Leaf River Storage Project
involving construction and operation of underground natural gas storage
and pipeline header facilities by Leaf River Energy
NOTICES: Rockies Express Pipeline LLC; technical conference,
Published: 2007-12-18
December 11, 2007.
On December 19, 2007, staff of the Office of Energy Projects (OEP)
will hold a technical conference concerning issues raised by Rockies
Express Pipeline LLC (Rockies Express) with two environmental
recommendations in the draft Environmental Impact Statement for the REX
East Project. In particular, the two environmental
NOTICES: Meetings; Sunshine Act,
Published: 2007-12-18
December 13, 2007.
The following notice of meeting is published pursuant to section
3(a) of the government in the Sunshine Act (Pub. L. No. 94409), 5 U.S.C. 552b:
Agency Holding Meeting: Federal Energy Regulatory Commission. Date and Time: December 20, 2007. 10 a.m.
Place: Room 2C, 888 First Street, NE., Washington, DC 20426.
Status: Open.
NOTICES: Colorado Interstate Gas Co.,
Published: 2007-12-18
December 11, 2007.
Take notice that on November 29, 2007, Colorado Interstate Gas
Company (CIG), Post Office Box 1087, Colorado Springs, Colorado 80944,
filed in Docket No. CP0830000, an application, pursuant to section 7
of the Natural Gas Act (NGA), for a certificate authorizing the
construction and operation of a new underground natural gas
NOTICES: FirstEnergy Generation Mansfield Unit 1 Corp.,
Published: 2007-12-18
December 11, 2007.
FirstEnergy Generation Mansfield Unit 1 Corp. (FEGM Unit 1) filed
an application for marketbased rate authority, with an accompanying
rate schedule. The proposed marketbased rate schedule provides for the
sale of energy and capacity at marketbased rates. FEGM Unit 1 also
requested waivers of various Commission regulations. In
NOTICES: Magic Valley Pipeline, L.P.,
Published: 2007-12-18
December 11, 2007.
Take notice that on November 30, 2007, Magic Valley Pipeline, L.P. (Magic Valley) filed a petition for approval of rates for
transportation services, pursuant to section 284.123(b)(2) of the
Commission's regulations. Magic Valley requests that the Commission
approve a maximum monthly reservation charge of $1.1669 per Dth,
NOTICES: New York Independent System Operator, Inc.,
Published: 2007-12-18
December 11, 2007.
Commission staff member Dr. Harry Singh (Office of Energy Markets
Regulation; 2025026341; harry.singh@ferc.gov) is assigned to help
resolve issues concerning the New York Independent System Operator,
Inc.'s (NYISO) proposal for Longterm Firm Transmission Rights (LTTRs),
which NYISO
NOTICES: Northern Renewable Energy (USA) Ltd.,
Published: 2007-12-18
December 11, 2007.
Northern Renewable Energy (USA) Ltd. (NREL USA) filed an
application for marketbased rate authority, with an accompanying rate
schedule. The proposed marketbased rate schedule provides for the sale
of energy, capacity and ancillary services at marketbased rates. NREL
USA so requested waivers of various Commission regulations.
NOTICES: Southern Company Services, Inc.,
Published: 2007-12-18
December 11, 2007.
Take notice that on December 4, 2007, Southern Company Service,
Inc., acting as agent for Alabama Power Company, Georgia Power Company,
Gulf Power Company, Mississippi Power Company, and Southern Power
Company (Southern Companies) filed an amendment to its November 16,
2007, Notice of Completion and Conformed Compliance
NOTICES: Southern Company Services, Inc.,
Published: 2007-12-18
December 11, 2007.
Take notice that on December 4, 2007, Southern Company Services,
Inc., acting as agent for Alabama Power Company, Georgia Power Company,
Gulf Power Company, Mississippi Power Company, and Southern Power
Company (collectively Southern Companies), filed a section 205 letter
to conform the definition of ``market information'',