Browse: Departments Dates Agencies
RIN ID: RIN 2115-AE47
CGD ID: [CGD01-01-038]
SUBJECT CATEGORY: Drawbridge Operation Regulations: West Bay, MA
DOCUMENT SUMMARY: The Coast Guard is changing the drawbridge operating regulations for the West Bay Bridge, at mile 1.2, across West Bay in Osterville, Massachusetts. This final rule will increase the advance notice requirement for April and extend the evening operating hours at the bridge during the boating season. This action is expected to better meet the present needs of navigation.
SUMMARY: Massachusetts,
On May 9, 2001, we published a notice of proposed rulemaking (NPRM) entitled Drawbridge Operation Regulations; West Bay, Massachusetts, in the Federal Register (66 FR 23638). We received no comment letters in response to the notice of proposed rulemaking. No public hearing was requested and none was held.
The West Bay Bridge, mile 1.2, across West Bay has a vertical clearance of 15 feet at mean high water and 17 feet at mean low water.
The existing regulations for the bridge listed at 33 CFR 117.622,
require the bridge to open on signal, April 1 through October 31, as follows:
(1) April 1 through June 14 and October 12 through October 31; 8 a.m. to 4 p.m.
(2) June 15 through June 30; 8 a.m. to 6 p.m.
(3) July 1 through Labor Day; 8 a.m. to 8 p.m.
(4) Labor Day through October 11; 8 a.m. to 5 p.m.
(5) At all other times from April 1 through October 31, the draw
shall open on signal if at least fourhours advance notice is given.
(6) From November 1 through March 31, the draw shall open on signal if at least twentyfour hours advance notice is given.
The bridge owner, the Town of Barnstable, asked the Coast Guard to
change the drawbridge operation regulations to allow the bridge to open on signal, from April 1 through April 30
[[Page 46524]]
if at least a twentyfour hours advance notice is given by calling the number posted at the bridge.
The bridge was authorized to remain closed for repairs in April for
the last two years. The number of bridge openings in April for the last five years are as follows:
1995 1996 1997 1998 1999 2000
54 46 45 70 0 0
In return for the advance notice requirement at all times in April, the bridge owner would crew the bridge two to three hours later at night during the boating season.
The bridge owner voluntarily expanded on signal service during the summer of 1999 and 2000, by extending the operating hours at the bridge at night. This was possible as a result of the cost savings derived from not crewing the bridge, 8 a.m. to 4 p.m., during the month of April while it was closed for repairs.
The bridge owner held a town meeting on January 25, 2001, in Osterville, Massachusetts, to receive verbal and written comment regarding this proposed change to the drawbridge operation regulations. The bridge has essentially operated for the past two years in accordance with the operating hours included in this rule. The proposed changes were fully supported by the local attendees at the special town meeting. Attendees at the meeting included the local marina operators, mariners and citizens of Osterville. Mariners can reach open water when the West Bay Bridge is not crewed by navigating through Cotuit. Discussion of Comments and Changes
The Coast Guard received no comment letters. No changes will be made to this final rule.
This rule is not a ``significant regulatory action'' under section 3(f) of Executive Order 12866 and does not require an assessment of potential costs and benefits under section 6(a)(3) of that Order. The Office of Management and Budget has not reviewed it under that Order. It is not ``significant'' under the regulatory policies and procedures of the Department of Transportation (DOT) (44 FR 11040; February 26, 1979). This conclusion is based on the fact that the bridge will open at all times for vessel traffic.
Under the Regulatory Flexibility Act (5 U.S.C. 601612) we considered whether this rule would have a significant economic impact on a substantial number of small entities. ``Small entities'' comprises small businesses, notfor profit organizations that are independently owned and operated and are not dominant in their fields, and governmental jurisdictions with populations less than 50,000.
The Coast Guard certifies under 5 U.S.C. 605(b) that this rule will not have a significant economic impact on a substantial number of small entities. This conclusion is based on the fact that the bridge will open at all times for vessel traffic.
This rule calls for no new collection of information under the Paperwork Reduction Act of 1995 (44 U.S.C. 35013520).
We have analyzed this rule under Executive Order 13132 and have determined that this rule does not have implications for federalism under that Order.
The Unfunded Mandates Reform Act of 1995 (2 U.S.C. 15311538) governs the issuance of Federal regulations that require unfunded mandates. An unfunded mandate is a regulation that requires a State, local, or tribal government or the private sector to incur direct costs without the Federal Government's having first provided the funds to pay those unfunded mandate costs. This rule will not impose an unfunded mandate.
This rule will not effect a taking of private property or otherwise have taking implications under E.O. 12630, Governmental Actions and Interference with Constitutionally Protected Property Rights Civil Justice Reform
This rule meets applicable standards in sections 3(a) and 3(b)(2) of E.O. 12988, Civil Justice Reform, to minimize litigation, eliminate ambiguity, and reduce burden
We have analyzed this rule under E.O. 13045, Protection of Children from Environmental Health Risks and Safety Risks. This rule is not an economically significant rule and does not concern an environmental risk to health or risk to safety that may disproportionately affect children.
The Coast Guard considered the environmental impact of this rule and concluded that under figure 21, paragraph (32)(e) of Commandant Instruction M16475.1C, this rule is categorically excluded from further environmental documentation because promulgation of changes to drawbridge regulations have been found to not have a significant effect on the environment. A written ``Categorical Exclusion Determination'' is not required for this final rule.
This rule does not have tribal implications under Executive Order 13175, Consultation and Coordination with Indian Tribal Governments, because it does not have substantial direct effect on one or more Indian tribes, on the relationship between the Federal Government and Indian tribes, or on the distribution of power and responsibilities between the Federal Government and Indian tribes.
We have analyzed this rule under Executive Order 13211, Actions
Concerning Regulations That Significantly Affect Energy Supply,
Distribution, or Use. We have determined that it is not a ``significant
energy action'' under that order because it is not a ``significant
regulatory action'' under Executive Order 12866 and is not likely to
have a significant adverse effect on the supply, distribution, or use
of energy. It has not been designated by the Administrator of the
Office of Information and Regulatory Affairs as a significant energy
action. Therefore, it does not require a Statement of Energy Effects under Executive Order 13211.
List of Subjects in 33 CFR Part 117
Bridges.
For the reasons set out in the preamble, the Coast Guard amends 33 CFR part 117 as follows:
[[Page 46525]]
1. The authority citation for part 117 continues to read as follows:
Authority: 33 U.S.C. 499; 49 CFR 1.46; 33 CFR 1.051(g); section 117.255 also issued under the authority of Pub. L. 102587, 106 Stat. 5039.
2. Section 117.622 is revised to read as follows: Sec. 117.622 West Bay
The draw of the West Bay Bridge, mile 1.2, at Osterville, shall operate as follows:
(1) From November 1 through April 30, the draw shall open on signal if at least a twentyfour hours advance notice is given.
(2) From May 1 through June 15, the draw shall open on signal from 8 a.m. to 6 p.m.
(3) From June 16 through September 30, the draw shall open on signal from 7 a.m. to 9 p.m.
(4) From October 1 through October 31, the draw shall open on signal from 8 a.m. to 6 p.m.
(5) At all other times from May 1 through October 31, the draw
shall open on signal if at least a fourhours advance notice is given by calling the number posted at the bridge.
Dated: August 17, 2001.
G.N. Naccara,
Rear Admiral, U.S. Coast Guard, Commander, First Coast Guard District.
[FR Doc. 0122394 Filed 9501; 8:45 am]
BILLING CODE 491015P
FOR FURTHER INFORMATION CONTACT Mr. John W. McDonald, Project Officer, First Coast Guard District, (617) 2238364.
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 47 CFR Part 73 26 CFR Part 1 40 CFR Part 180 33 CFR Part 117 50 CFR Part 17 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 40 CFR Part 63 33 CFR Part 100 50 CFR Part 622 50 CFR Part 660 26 CFR Part 301 44 CFR Part 65 39 CFR Part 111 40 CFR Part 300 6 CFR Part 5 40 CFR Part 271 47 CFR Part 64 40 CFR Parts 52 and 81 50 CFR Part 665 10 CFR Part 50 44 CFR Part 64 49 CFR Part 571 39 CFR Part 3020