Browse: Departments Dates Agencies
RIN ID: RIN 2115-AE47
CGD ID: [CGD01-02-007]
SUBJECT CATEGORY: Drawbridge Operation Regulations: Harlem River, NY
DOCUMENT SUMMARY: The Coast Guard is temporarily changing the drawbridge operation regulations for the Madison Avenue Bridge, mile 2.3 and the Macombs Dam Bridge, at mile 3.2, both across the Harlem River at New York City, New York. This temporary rule will allow the bridges to remain in the closed position at various times to facilitate necessary bridge maintenance.
SUMMARY: New York,
Pursuant to 5 U.S.C. 553, a notice of proposed rulemaking (NPRM) was not published for this regulation. Good cause exists for not publishing a NPRM and for making this regulation effective in less than 30 days after publication in the Federal Register.
These closures are not expected to impact navigation because the vessels that normally use this waterway were designed to fit under the bridges on the Harlem River without requiring bridge openings. There have been no requests to open these bridges for several years. Accordingly, an NPRM was considered unnecessary and the rule may be made effective in less than 30 days after publication.
The Madison Avenue Bridge has a vertical clearance in the closed position of 25 feet at mean high water and 29 feet at mean low water. The Macombs Dam Bridge has a vertical clearance in the closed position of 27 feet at mean high water and 32 feet at mean low water. The existing drawbridge operating regulations, listed at 33 CFR 117.789(c), require the bridges to open on signal from 10 a.m. to 5 p.m., after a fourhour advance notice is given.
The owner of the bridges, the New York City Department of Transportation (NYCDOT), requested a temporary final rule to facilitate scheduled maintenance and replacement of electrical and mechanical systems at the bridges. These bridge closures are not expected to effect vessel traffic because there have been no requests to open the bridges for several years. Vessels that can pass under the bridges without openings may do so at all times during these closures. Regulatory Evaluation
This rule is not a ``significant regulatory action'' under section 3(f) of Executive Order 12866 and does not require an assessment of potential costs and benefits under section 6(a)(3) of that Order. The Office of Management and Budget has not reviewed it under that Order. It is not ``significant'' under the regulatory policies and procedures of the Department of Transportation (DOT) (44 FR 11040; February 26, 1979). This conclusion is based on the fact that keeping the bridges closed should have no impact on navigation because the bridges have not had any requests to open for several years.
Under the Regulatory Flexibility Act (5 U.S.C. 601612) we considered whether this rule would have a significant economic impact on a substantial number of small entities. ``Small entities'' comprises small businesses, notfor profit organizations that are independently owned and operated and are not dominant in their fields, and governmental jurisdictions with populations less than 50,000.
The Coast Guard certifies under 5 U.S.C. 605(b) that this rule will not have a significant economic impact on a substantial number of small entities. This conclusion is based on the fact that the closure of the bridges should have no impact on navigation because the bridges have not had any requests to open for several years.
This rule calls for no new collection of information under the Paperwork Reduction Act of 1995 (44 U.S.C. 35013520).
We have analyzed this rule under Executive Order 13132 and have determined that this rule does not have implications for federalism under that Order.
The Unfunded Mandates Reform Act of 1995 (2 U.S.C. 15311538) governs the issuance of Federal regulations that require unfunded mandates. An unfunded mandate is a regulation that requires a State, local, or tribal government or the private sector to incur direct costs without the Federal Government's having first provided the funds to pay those unfunded mandate costs. This rule will not impose an unfunded mandate.
This rule will not effect a taking of private property or otherwise have taking implications under Executive Order 12630, Governmental Actions and Interference with Constitutionally Protected Property Rights.
This rule meets applicable standards in sections 3(a) and 3(b)(2) of Executive Order 12988, Civil Justice Reform, to minimize litigation, eliminate ambiguity, and reduce burden.
We have analyzed this rule under Executive Order 13045, Protection
of Children from Environmental Health Risks and Safety Risks. This rule
is not an economically significant rule and does not concern an environmental risk to health or risk to safety that may
disproportionately affect children.
The Coast Guard considered the environmental impact of this rule
and concluded that under figure 21, paragraph (32)(e) of Commandant
Instruction M16475.1C, this rule is categorically excluded from further
environmental documentation because promulgation of changes to
drawbridge regulations have been found to not have a significant effect on the environment. A written ``Categorical Exclusion
[[Page 6648]]
Determination'' is not required for this final rule.
List of Subjects in 33 CFR Part 117
Bridges.
For the reasons set out in the preamble, the Coast Guard amends 33 CFR part 117 as follows:
1. The authority citation for part 117 continues to read as follows:
Authority: 33 U.S.C. 499; 49 CFR 1.46; 33 CFR 1.051(g); section 117.255 also issued under the authority of Pub. L. 102587, 106 Stat. 5039.
2. From February 18, 2002, through February 28, 2003, Sec. 117.789
is temporarily amended by suspending paragraph (c) and adding a new paragraph (g) to read as follows:
Sec. 117.789 Harlem River.
* * * * *
(g) The draws of the bridges at 103rd Street, mile 0.0, Willis
Avenue, mile 1.5, 3rd Avenue, mile 1.9, Madison Avenue, mile 2.3, 145th
Street, mile 2.8, Macombs Dam, mile 3.2, the 207th Street, mile 6.0,
and the two Broadway bridges, mile 6.8, shall open on signal from 10
a.m. to 5 p.m. if at least a fourhour advance notice is given to the
New York City Highway Radio (Hotline) Room; except that the Madison
Avenue Bridge, mile 2.3, need not open for vessel traffic from February
18 through May 24, 2002 and the Macombs Dam Bridge, mile 3.2, need not
open for vessel traffic from April 2 through June 30, 2002 and from December 1, 2002 through February 28, 2003.
Dated: January 23, 2002.
G.N. Naccara,
Rear Admiral, U. S. Coast Guard, Commander, First Coast Guard District.
[FR Doc. 023517 Filed 21202; 8:45 am]
BILLING CODE 491015U
FOR FURTHER INFORMATION CONTACT Mr. Joe Arca, Project Officer, First Coast Guard District, (212) 6687165.
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 26 CFR Part 1 40 CFR Part 180 47 CFR Part 73 50 CFR Part 17 33 CFR Part 117 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 33 CFR Part 100 40 CFR Part 63 26 CFR Part 301 50 CFR Part 622 39 CFR Part 111 40 CFR Part 300 44 CFR Part 65 50 CFR Part 660 40 CFR Part 271 40 CFR Parts 52 and 81 47 CFR Part 64 50 CFR Part 665 49 CFR Part 571 44 CFR Part 64 21 CFR Part 522 14 CFR Part 23 47 CFR Part 76