Docket ID: [Docket Nos. 50-348 and 50-364]
SUBJECT CATEGORY: Southern Nuclear Operating Company, Joseph M. Farley Nuclear Plant; Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process
DOCUMENT SUMMARY:
Southern Nuclear Operating Company (SNC) has submitted an application for renewal of Facility Operating Licenses, NPF2 and NPF8 for an additional 20 years of operation at the Joseph M. Farley Nuclear Plant, Units 1 and 2. The Farley Nuclear Plant (FNP) is located in Houston County, Alabama about 16.5 miles east of the City of Dothan, Alabama. The operating licenses for Farley Nuclear Plant, Units 1 and 2, expire on June 25, 2017, and March 31, 2021, respectively. The application for renewal was received on September 15, 2003, pursuant to 10 CFR part 54. A notice of receipt and availability of the application, which included the environmental report (ER), was published in the Federal Register on October 6, 2003, (68 FR 57715). A notice of acceptance for docketing of the application for renewal of the facility operating license was published in the Federal Register on October 30, 2003, (68 FR 68135). A notice of an opportunity for a hearing regarding the application was published in the Federal Register on November 5, 2003, (68 FR 62640). The purpose of this notice is to inform the public that the U.S. Nuclear Regulatory Commission (NRC) will be preparing an environmental impact statement (EIS) in support of the review of the license renewal application and to provide the public an opportunity to participate in the environmental scoping process, as defined in 10 CFR 51.29. In addition, as outlined in 36 CFR 800.8, ``Coordination with the National Environmental Policy Act,'' the NRC plans to coordinate compliance with section 106 of the National Historic Preservation Act in meeting the requirements of the National Environmental Policy Act (NEPA).
In accordance with 10 CFR 51.53(c) and 10 CFR 54.23, SNC submitted
the ER as part of the application. The ER was prepared pursuant to 10
CFR part 51 and is available for public inspection at the NRC Public
Document Room (PDR), located at One White Flint North, 11555 Rockville
Pike (first floor), Rockville, Maryland, or from the Publicly Available
Records component of NRC's Agencywide Documents Access and Management
System (ADAMS). ADAMS is accessible at http://www.nrc.gov/readingrm/adams.html
, which provides access through the NRC's Electronic Reading
Room link. Persons who do not have access to ADAMS, or who encounter
problems in accessing the documents located in ADAMS, should contact
the NRC's PDR Reference staff at 18003974209, or 3014154737, or by email to pdr@nrc.gov. The application may also be viewed on the
Internet at http://www.nrc.gov/reactors/operating/licensing/renewal/applications/farley.html. In addition, the Houston Love Memorial
Library, 212 West Burdeshaw Street, Dothan, Alabama and the Lucy Maddox
Memorial Library, 11880 Columbia Street, Blakely, Georgia have agreed to make the ER available for public inspection.
This notice advises the public that the NRC intends to gather the information necessary to prepare a plantspecific supplement to the Commission's ``Generic Environmental Impact Statement (GEIS) for License Renewal of Nuclear Plants,'' (NUREG1437) in support of the review of the application for renewal of the FNP operating licenses for an additional 20 years. Possible alternatives to the proposed action (license renewal) include no action and reasonable alternative energy sources. The NRC is required by 10 CFR 51.95 to prepare a supplement to the GEIS in connection with the renewal of an operating license. This notice is being published in accordance with the National Environmental Policy Act (NEPA) and the NRC's regulations found in 10 CFR part 51.
The NRC will first conduct a scoping process for the supplement to the GEIS and, as soon as practicable thereafter, will prepare a draft supplement to the GEIS for public comment. Participation in the scoping process by members of the public and local, State, Tribal, and Federal government agencies is encouraged. The scoping process for the supplement to the GEIS will be used to accomplish the following:
a. Define the proposed action which is to be the subject of the supplement to the GEIS.
b. Determine the scope of the supplement to the GEIS and identify the significant issues to be analyzed in depth.
c. Identify and eliminate from detailed study those issues that are peripheral or that are not significant.
d. Identify any environmental assessments and other EISs that are being or will be prepared that are related to, but are not part of the scope of the supplement to the GEIS being considered.
e. Identify other environmental review and consultation requirements related to the proposed action.
f. Indicate the relationship between the timing of the preparation of the environmental analyses and the Commission's tentative planning and decisionmaking schedule.
g. Identify any cooperating agencies and, as appropriate, allocate assignments for preparation and schedules for completing the supplement to the GEIS to the NRC and any cooperating agencies.
h. Describe how the supplement to the GEIS will be prepared, and include any contractor assistance to be used.
The NRC invites the following entities to participate in the scoping:
a. The applicant, Southern Nuclear Operating Company.
b. Any Federal agency that has jurisdiction by law or special expertise with respect to any environmental impact involved, or that is authorized to develop and enforce relevant environmental standards.
c. Affected State and local government agencies, including those authorized to develop and enforce relevant environmental standards.
d. Any affected Indian tribe.
e. Any person who requests or has requested an opportunity to participate in the scoping process.
f. Any person who intends to petition for leave to intervene.
In accordance with 10 CFR 51.26, the scoping process for an EIS may include
[[Page 68126]]
a public scoping meeting to help identify significant issues related to
a proposed activity and to determine the scope of issues to be
addressed in an EIS. The NRC has decided to hold public meetings for
the FNP license renewal supplement to the GEIS. The scoping meetings
will be held at the Quality Inn, 3053 Ross Clark Circle, Dothan,
Alabama, on Thursday, January 8, 2004. There will be two sessions to
accommodate interested parties. The first session will convene at 1:30
p.m. and will continue until 4:30 p.m., as necessary. The second
session will convene at 7 p.m. with a repeat of the overview portions
of the meeting and will continue until 10 p.m., as necessary. Both
meetings will be transcribed and will include: (1) An overview by the
NRC staff of the NEPA environmental review process, the proposed scope
of the supplement to the GEIS, and the proposed review schedule; and
(2) the opportunity for interested government agencies, organizations,
and individuals to submit comments or suggestions on the environmental
issues or the proposed scope of the supplement to the GEIS.
Additionally, the NRC staff will host informal discussions one hour
before the start of each session at the Quality Inn. No formal comments
on the proposed scope of the supplement to the GEIS will be accepted
during the informal discussions. To be considered, comments must be
provided either at the transcribed public meetings or in writing, as
discussed below. Persons may register to attend or present oral
comments at the meetings on the scope of the NEPA review by contacting
Mr. Cushing, by telephone at 18003685642, extension 1424, or by Internet to the NRC at FarleyEIS@nrc.gov no later than January 2, 2004.
Members of the public may also register to speak at the meeting within
15 minutes of the start of each session. Individual oral comments may
be limited by the time available, depending on the number of persons
who register. Members of the public who have not registered may also
have an opportunity to speak, if time permits. Public comments will be
considered in the scoping process for the supplement to the GEIS. Mr.
Cushing will need to be contacted no later than December 17, 2003, if
special equipment or accommodations are needed to attend or present
information at the public meeting, so that the NRC staff can determine whether the request can be accommodated.
Members of the public may send written comments on the environmental scope of the FNP license renewal review to the Chief, Rules and Directives Branch, Division of Administrative Services, Office of Administration, Mailstop T6D59, U.S. Nuclear Regulatory Commission, Washington, DC 205550001, and should cite the publication date and page number of this Federal Register notice. Comments may also be delivered to the NRC, Room T6D59, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland, from 7:30 a.m. to 4:15 p.m. during Federal workdays. To be considered in the scoping process, written comments should be postmarked by February 6, 2004. Electronic comments may be sent by the Internet to the NRC at FarleyEIS@nrc.gov and should be sent no later than February 6, 2004, to be considered in the scoping process. Comments will be available electronically and accessible through ADAMS at http://www.nrc.gov/readingrm/adams.html.
Participation in the scoping process for the supplement to the GEIS does not entitle participants to become parties to the proceeding to which the supplement to the GEIS relates. Notice of opportunity for a hearing regarding the renewal application was the subject of the aforementioned Federal Register notice (68 FR 62640). Matters related to participation in any hearing are outside the scope of matters to be discussed at this public meeting.
At the conclusion of the scoping process, the NRC will prepare a concise summary of the determination and conclusions reached, including the significant issues identified, and will send a copy of the summary to each participant in the scoping process. The summary will also be available for inspection in ADAMS at http://www.nrc.gov/readingrm/adams.html. The staff will then prepare and issue for comment the draft supplement to the GEIS, which will be the subject of separate notices and separate public meetings. Copies will be available for public inspection at the abovementioned addresses, and one copy per request will be provided free of charge. After receipt and consideration of the comments, the NRC will prepare a final supplement to the GEIS, which will also be available for public inspection.
Information about the proposed action, the supplement to the GEIS, and the scoping process may be obtained from Mr. Cushing at the aforementioned telephone number or email address.
Dated at Rockville, Maryland, this 26th day of November, 2003.
For the Nuclear Regulatory Commission.
PaoTsin Kuo,
Program Director, License Renewal and Environmental Impacts Program,
Division of Regulatory Improvement Programs, Office of Nuclear Reactor Regulation.
[FR Doc. 0330247 Filed 12403; 8:45 am]
BILLING CODE 759001P
SUMMARY: Southern Nuclear Operating Co.,
DOCUMENT BODY 2:
Southern Nuclear Operating Company (SNC) has submitted an application for renewal of Facility Operating Licenses, NPF2 and NPF8 for an additional 20 years of operation at the Joseph M. Farley Nuclear Plant, Units 1 and 2. The Farley Nuclear Plant (FNP) is located in Houston County, Alabama about 16.5 miles east of the City of Dothan, Alabama. The operating licenses for Farley Nuclear Plant, Units 1 and 2, expire on June 25, 2017, and March 31, 2021, respectively. The application for renewal was received on September 15, 2003, pursuant to 10 CFR part 54. A notice of receipt and availability of the application, which included the environmental report (ER), was published in the Federal Register on October 6, 2003, (68 FR 57715). A notice of acceptance for docketing of the application for renewal of the facility operating license was published in the Federal Register on October 30, 2003, (68 FR 68135). A notice of an opportunity for a hearing regarding the application was published in the Federal Register on November 5, 2003, (68 FR 62640). The purpose of this notice is to inform the public that the U.S. Nuclear Regulatory Commission (NRC) will be preparing an environmental impact statement (EIS) in support of the review of the license renewal application and to provide the public an opportunity to participate in the environmental scoping process, as defined in 10 CFR 51.29. In addition, as outlined in 36 CFR 800.8, ``Coordination with the National Environmental Policy Act,'' the NRC plans to coordinate compliance with section 106 of the National Historic Preservation Act in meeting the requirements of the National Environmental Policy Act (NEPA).
In accordance with 10 CFR 51.53(c) and 10 CFR 54.23, SNC submitted
the ER as part of the application. The ER was prepared pursuant to 10
CFR part 51 and is available for public inspection at the NRC Public
Document Room (PDR), located at One White Flint North, 11555 Rockville
Pike (first floor), Rockville, Maryland, or from the Publicly Available
Records component of NRC's Agencywide Documents Access and Management
System (ADAMS). ADAMS is accessible at http://www.nrc.gov/readingrm/adams.html
, which provides access through the NRC's Electronic Reading
Room link. Persons who do not have access to ADAMS, or who encounter
problems in accessing the documents located in ADAMS, should contact
the NRC's PDR Reference staff at 18003974209, or 3014154737, or by email to pdr@nrc.gov. The application may also be viewed on the
Internet at http://www.nrc.gov/reactors/operating/licensing/renewal/applications/farley.html. In addition, the Houston Love Memorial
Library, 212 West Burdeshaw Street, Dothan, Alabama and the Lucy Maddox
Memorial Library, 11880 Columbia Street, Blakely, Georgia have agreed to make the ER available for public inspection.
This notice advises the public that the NRC intends to gather the information necessary to prepare a plantspecific supplement to the Commission's ``Generic Environmental Impact Statement (GEIS) for License Renewal of Nuclear Plants,'' (NUREG1437) in support of the review of the application for renewal of the FNP operating licenses for an additional 20 years. Possible alternatives to the proposed action (license renewal) include no action and reasonable alternative energy sources. The NRC is required by 10 CFR 51.95 to prepare a supplement to the GEIS in connection with the renewal of an operating license. This notice is being published in accordance with the National Environmental Policy Act (NEPA) and the NRC's regulations found in 10 CFR part 51.
The NRC will first conduct a scoping process for the supplement to the GEIS and, as soon as practicable thereafter, will prepare a draft supplement to the GEIS for public comment. Participation in the scoping process by members of the public and local, State, Tribal, and Federal government agencies is encouraged. The scoping process for the supplement to the GEIS will be used to accomplish the following:
a. Define the proposed action which is to be the subject of the supplement to the GEIS.
b. Determine the scope of the supplement to the GEIS and identify the significant issues to be analyzed in depth.
c. Identify and eliminate from detailed study those issues that are peripheral or that are not significant.
d. Identify any environmental assessments and other EISs that are being or will be prepared that are related to, but are not part of the scope of the supplement to the GEIS being considered.
e. Identify other environmental review and consultation requirements related to the proposed action.
f. Indicate the relationship between the timing of the preparation of the environmental analyses and the Commission's tentative planning and decisionmaking schedule.
g. Identify any cooperating agencies and, as appropriate, allocate assignments for preparation and schedules for completing the supplement to the GEIS to the NRC and any cooperating agencies.
h. Describe how the supplement to the GEIS will be prepared, and include any contractor assistance to be used.
The NRC invites the following entities to participate in the scoping:
a. The applicant, Southern Nuclear Operating Company.
b. Any Federal agency that has jurisdiction by law or special expertise with respect to any environmental impact involved, or that is authorized to develop and enforce relevant environmental standards.
c. Affected State and local government agencies, including those authorized to develop and enforce relevant environmental standards.
d. Any affected Indian tribe.
e. Any person who requests or has requested an opportunity to participate in the scoping process.
f. Any person who intends to petition for leave to intervene.
In accordance with 10 CFR 51.26, the scoping process for an EIS may include
[[Page 68126]]
a public scoping meeting to help identify significant issues related to
a proposed activity and to determine the scope of issues to be
addressed in an EIS. The NRC has decided to hold public meetings for
the FNP license renewal supplement to the GEIS. The scoping meetings
will be held at the Quality Inn, 3053 Ross Clark Circle, Dothan,
Alabama, on Thursday, January 8, 2004. There will be two sessions to
accommodate interested parties. The first session will convene at 1:30
p.m. and will continue until 4:30 p.m., as necessary. The second
session will convene at 7 p.m. with a repeat of the overview portions
of the meeting and will continue until 10 p.m., as necessary. Both
meetings will be transcribed and will include: (1) An overview by the
NRC staff of the NEPA environmental review process, the proposed scope
of the supplement to the GEIS, and the proposed review schedule; and
(2) the opportunity for interested government agencies, organizations,
and individuals to submit comments or suggestions on the environmental
issues or the proposed scope of the supplement to the GEIS.
Additionally, the NRC staff will host informal discussions one hour
before the start of each session at the Quality Inn. No formal comments
on the proposed scope of the supplement to the GEIS will be accepted
during the informal discussions. To be considered, comments must be
provided either at the transcribed public meetings or in writing, as
discussed below. Persons may register to attend or present oral
comments at the meetings on the scope of the NEPA review by contacting
Mr. Cushing, by telephone at 18003685642, extension 1424, or by Internet to the NRC at FarleyEIS@nrc.gov no later than January 2, 2004.
Members of the public may also register to speak at the meeting within
15 minutes of the start of each session. Individual oral comments may
be limited by the time available, depending on the number of persons
who register. Members of the public who have not registered may also
have an opportunity to speak, if time permits. Public comments will be
considered in the scoping process for the supplement to the GEIS. Mr.
Cushing will need to be contacted no later than December 17, 2003, if
special equipment or accommodations are needed to attend or present
information at the public meeting, so that the NRC staff can determine whether the request can be accommodated.
Members of the public may send written comments on the environmental scope of the FNP license renewal review to the Chief, Rules and Directives Branch, Division of Administrative Services, Office of Administration, Mailstop T6D59, U.S. Nuclear Regulatory Commission, Washington, DC 205550001, and should cite the publication date and page number of this Federal Register notice. Comments may also be delivered to the NRC, Room T6D59, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland, from 7:30 a.m. to 4:15 p.m. during Federal workdays. To be considered in the scoping process, written comments should be postmarked by February 6, 2004. Electronic comments may be sent by the Internet to the NRC at FarleyEIS@nrc.gov and should be sent no later than February 6, 2004, to be considered in the scoping process. Comments will be available electronically and accessible through ADAMS at http://www.nrc.gov/readingrm/adams.html.
Participation in the scoping process for the supplement to the GEIS does not entitle participants to become parties to the proceeding to which the supplement to the GEIS relates. Notice of opportunity for a hearing regarding the renewal application was the subject of the aforementioned Federal Register notice (68 FR 62640). Matters related to participation in any hearing are outside the scope of matters to be discussed at this public meeting.
At the conclusion of the scoping process, the NRC will prepare a concise summary of the determination and conclusions reached, including the significant issues identified, and will send a copy of the summary to each participant in the scoping process. The summary will also be available for inspection in ADAMS at http://www.nrc.gov/readingrm/adams.html. The staff will then prepare and issue for comment the draft supplement to the GEIS, which will be the subject of separate notices and separate public meetings. Copies will be available for public inspection at the abovementioned addresses, and one copy per request will be provided free of charge. After receipt and consideration of the comments, the NRC will prepare a final supplement to the GEIS, which will also be available for public inspection.
Information about the proposed action, the supplement to the GEIS, and the scoping process may be obtained from Mr. Cushing at the aforementioned telephone number or email address.
Dated at Rockville, Maryland, this 26th day of November, 2003.
For the Nuclear Regulatory Commission.
PaoTsin Kuo,
Program Director, License Renewal and Environmental Impacts Program,
Division of Regulatory Improvement Programs, Office of Nuclear Reactor Regulation.
[FR Doc. 0330247 Filed 12403; 8:45 am]
BILLING CODE 759001P
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 47 CFR Part 73 26 CFR Part 1 40 CFR Part 180 33 CFR Part 117 50 CFR Part 17 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 33 CFR Part 100 40 CFR Part 63 50 CFR Part 622 44 CFR Part 65 50 CFR Part 660 26 CFR Part 301 39 CFR Part 111 40 CFR Part 300 6 CFR Part 5 40 CFR Part 271 47 CFR Part 64 40 CFR Parts 52 and 81 50 CFR Part 665 44 CFR Part 64 10 CFR Part 50 49 CFR Part 571 47 CFR Part 76