Browse: Departments Dates Agencies
RIN ID: RIN 1625-AA09
CGD ID: [CGD08-05-034]
SUBJECT CATEGORY: Drawbridge Operation Regulation; Tchoutacabouffa River, Cedar Lake, MS
DOCUMENT SUMMARY: The Commander, Eighth Coast Guard District, has temporarily changed the regulation governing the operation of the Cedar Lake Road Swing Span drawbridge across the Tchoutacabouffa River, mile 8.0, at Cedar Lake, Harrison County, Mississippi. The rule states that the draw of the bridge shall open on signal with twentyfour hours notice; except that the draw will remain closed to navigation Monday through Friday from June 27 through October 28, 2005 with the exception of July 4, 2005. However, from August 1 through September 23, 2005 it will open on signal with twentyfour hours notice every other weekend, beginning with the weekend of August 13, 2005. The closure is necessary for remedial structural repairs to be made to the bridge that are essential for the continued operation of the draw span.
SUMMARY: Mississippi,
We did not publish a notice of proposed rulemaking (NPRM) for this regulation. Under 5 U.S.C. 553(b)(B), the Coast Guard finds that good cause exists for not publishing an NPRM. The City of Biloxi has recently become responsible for maintenance of this bridge and upon initial inspection, discovered that remedial structural repairs must be done expediently to prevent the waterway from being obstructed. As a result, publishing an NPRM would be contrary to the public interest. Good Cause for Making Rule Effective in Less Than 30 Days
Under 5 U.S.C. 553(d)(3), the Coast Guard finds that good cause exists for making this rule effective in less than 30 days after publication in the Federal Register. The required repairs must be done expediently because there is a substantial risk that emergency breakdowns will occur, causing the waterway to be obstructed for lengthy periods of time.
The City of Biloxi has requested a temporary rule changing the
operation of the bascule span drawbridge across the Tchoutacabouffa
River, mile 8.0 at Cedar Lake, Harrison County, Mississippi. Recently,
maintenance responsibility for the bridge was transferred from Harrison
County to the City of Biloxi. City bridge engineers conducted an
inspection of the bridge and found that the swing span of the bridge
had numerous badly deteriorated steel structural members. In order to
maintain the operation of the swing span in a safe, efficient manner,
expedient remedial repair is needed. The contractor for the City of
Biloxi plans to remove and replace existing structural members from
June 27 through August 1, 2005. This will require closures of five days
at a time. During the period between August 1 and September 23, 2005,
the bridge will need to be closed to navigation to facilitate replacing
steel members and adding additional steel members then balancing the
swing span. During the period between September 23 and October 28,
2005, the contractor will sand blast and paint the entire structure.
This rule allows the draw of the bridge to remain closed to navigation
continuously, Monday through Friday from June 27 through October 28,
2005. It will open on signal with twentyfour hours notice every weekend during this period, except from August 1, 2005
[[Page 34352]]
through September 23, 2005 when it will open on signal with twentyfour
hours notice every other weekend beginning with the weekend of August 13, 2005.
The bridge has a vertical clearance of 5 feet above mean high water in the closedtonavigation position and unlimited in the opento navigation position. Bridge tender logs show that the bridge opens to pass navigation approximately four times per month during the summer and fall. The majority of vessels that require an opening of the draw are recreational vessels. Bridge tender logs show that during the period between June 27, 2004 and October 28, 2004, the bridge was opened only four times for commercial fishing vessels and none for tugs with tows. The City of Biloxi has contacted the primary waterway users of the waterway, including commercial users, and advised them of the planned closures. The City of Biloxi has indicated to the Coast Guard that the waterway users will be able to schedule their operations when the bridge will be able to open to pass marine traffic.
Presently, title 33, Code of Federal Regulations (CFR), part 117.685 states: The draw of the Cedar Lake Road Bridge over the Tchoutacabouffa River, mile 8.0, shall open on signal if at least twentyfour hours notice is given.
This rule is not a ``significant regulatory action'' under section 3(f) of Executive Order 12866, Regulatory Planning and Review, and does not require an assessment of potential costs and benefits under section 6(a)(3) of that Order. The Office of Management and Budget has not reviewed it under that Order. It is not ``significant'' under the regulatory policies and procedures of the Department of Homeland Security (DHS).
There is not expected to be a significant impact due to the infrequency of vessel transits through the bridge. The City of Biloxi has contacted the users of the waterway who have indicated that they will be able to schedule their transits during the periods when the bridge will open to pass marine traffic.
Under the Regulatory Flexibility Act (5 U.S.C. 601612), we have considered whether this rule would have a significant economic impact on a substantial number of small entities. The term ``small entities'' comprises small businesses, notforprofit organizations that are independently owned and operated and are not dominant in their fields, and governmental jurisdictions with populations of less than 50,000. The Coast Guard certifies under 5 U.S.C. 605(b) that this temporary rule will not have a significant economic impact on a substantial number of small entities.
This rule may affect the following entities, some of which may be small entities: The owners or operators of vessels intending to transit through the Cedar Lake Road Bridge across the Tchoutacabouffa River during the closure. As stated above, there is not expected to be a significant impact due to the infrequency of vessel transits through the bridge. The City of Biloxi has contacted the users of the waterway who have indicated that they will be able to schedule their transits during the periods when the bridge will open to pass marine traffic. Assistance for Small Entities
Under section 213(a) of the Small Business Regulatory Enforcement Fairness Act of 1996 (Pub. L. 104121), we want to assist small entities in understanding this rule so that they can better evaluate its effects on them and participate in the rulemaking process. Small businesses may send comments on the actions of Federal employees who enforce, or otherwise determine compliance with, Federal regulations to the Small Business and Agriculture Regulatory Enforcement Ombudsman and the Regional Small Business Regulatory Fairness Boards. The Ombudsman evaluates these actions annually and rates each agency?s responsiveness to small business. If you wish to comment on actions by employees of the Coast Guard, call 1888REGFAIR (18887343247).
This rule calls for no new collection of information under the Paperwork Reduction Act of 1995 (44 U.S.C. 35013520).
A rule has implications for federalism under Executive Order 13132, Federalism, if it has a substantial direct effect on State or local governments and would either preempt State law or impose a substantial direct cost of compliance on them. We have analyzed this rule under that Order and have determined that it does not have implications for federalism.
The Unfunded Mandates Reform Act of 1995 (2 U.S.C. 15311538) requires Federal agencies to assess the effects of their discretionary regulatory actions. In particular, the Act addresses actions that may result in the expenditure by a State, local, or tribal government, in the aggregate, or by the private sector of $100,000,000 or more in any one year. Though this rule will not result in such an expenditure, we do discuss the effects of this rule elsewhere in the preamble. Taking of Private Property
This rule will not affect a taking of private property or otherwise have taking implications under Executive Order 12630, Governmental Actions and Interference with Constitutionally Protected Property Rights.
This rule meets applicable standards in sections 3(a) and 3(b)(2) of Executive Order 12988, Civil Justice Reform, to minimize litigation, eliminate ambiguity, and reduce burden.
We have analyzed this rule under Executive Order 13045, Protection
of Children from Environmental Health Risks and Safety Risks. This rule
is not an economically significant rule and does not cause an environmental risk to health or risk to safety that may
disproportionately affect children.
This rule does not have tribal implications under Executive Order 13175, Consultation and Coordination with Indian Tribal Governments, because it does not have a substantial direct effect on one or more Indian tribes, on the relationship between the Federal Government and Indian tribes, or on the distribution of power and responsibilities between the Federal Government and Indian tribes.
We have analyzed this rule under Executive Order 13211, Actions
Concerning Regulations That Significantly Affect Energy Supply,
Distribution, or Use. We have determined that it is not a ``significant
energy action'' under that order because it is not a ``significant
regulatory action'' under Executive Order 12866 and is not likely to
have a significant adverse effect on the supply, distribution, or use
of energy. The Administrator of the Office of Information and
Regulatory Affairs has not designated it as a significant energy
action. Therefore, it does not require a Statement of Energy Effects under Executive Order 13211.
[[Page 34353]]
The National Technology Transfer and Advancement Act (NTTAA) (15 U.S.C. 272 note) directs agencies to use voluntary consensus standards in their regulatory activities unless the agency provides Congress, through the Office of Management and Budget, with an explanation of why using these standards would be inconsistent with applicable law or otherwise impractical. Voluntary consensus standards are technical standards (e.g., specifications of materials, performance, design, or operation; test methods; sampling procedures; and related management systems practices) that are developed or adopted by voluntary consensus standards bodies. This rule does not use technical standards. Therefore, we did not consider the use of voluntary consensus standards.
We have analyzed this rule under Commandant Instruction M16475.1D,
which guides the Coast Guard in complying with the National
Environmental Policy Act of 1969 (NEPA) (42 U.S.C. 43214370f), and
have concluded that there are no factors in this case that would limit
the use of a categorical exclusion under section 2.B.2 of the
Instruction. Therefore, this temporary rule is categorically excluded,
under figure 21, paragraph (32)(e), of the Instruction, from further
environmental documentation because it modifies an existing bridge operation regulation.
List of Subjects in 33 CFR Part 117
Bridges.
Regulations
For the reasons set out in the preamble, the Coast Guard amends 33 CFR part 117 as follows:
PART 117DRAWBRIDGE OPERATION REGULATIONS
1. The authority citation for part 117 continues to read as follows:
Authority: 33 U.S.C. 499; Department of Homeland Security
Delegation No. 0170.1; 33 CFR 1.051(g); section 117.255 also issued under the authority of Pub. L. 102587, 106 Stat. 5039.
2. From June 27, 2005 to October 28, 2005, Sec. 117.685 is suspended and a new Sec. 117.T684 is added to read as follows:
The draw of the Cedar Lake Road swing span bridge, Tchoutacabouffa
River, mile 8.0, will open on signal with twentyfour hours notice;
except that the draw will remain closed to navigation Monday through
Friday with the exception of July 4, 2005. However, from August 1, 2005
through September 23, 2005 it will open on signal with twentyfour
hours notice every other weekend beginning with the weekend of August 13, 2005.
Dated: June 3, 2005.
R.F. Duncan,
Rear Admiral, U.S. Coast Guard, Commander, Eighth Coast Guard District. [FR Doc. 0511673 Filed 61305; 8:45 am]
BILLING CODE 491015P
FOR FURTHER INFORMATION CONTACT Phil Johnson, Bridge Administration Branch, (504) 5892965.
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 47 CFR Part 73 26 CFR Part 1 40 CFR Part 180 33 CFR Part 117 50 CFR Part 17 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 40 CFR Part 63 33 CFR Part 100 50 CFR Part 622 50 CFR Part 660 44 CFR Part 65 26 CFR Part 301 39 CFR Part 111 40 CFR Part 300 6 CFR Part 5 40 CFR Part 271 47 CFR Part 64 40 CFR Parts 52 and 81 50 CFR Part 665 10 CFR Part 50 44 CFR Part 64 49 CFR Part 571 39 CFR Part 3020