RIN ID: RIN 1625-AA-09
CGD ID: [CGD05-06-040]
SUBJECT CATEGORY: Drawbridge Operation Regulations; Potomac River, Between Maryland and Virginia
DOCUMENT SUMMARY: The Commander, Fifth Coast Guard District, has approved a temporary deviation from the regulations governing the operation of the Woodrow Wilson Memorial (I95) Bridge, mile 103.8, across the Potomac River between Alexandria, Virginia and Oxon Hill, Maryland. This deviation allows the drawbridge to remain closedtonavigation from 8 p.m. on June 9, 2006, until 5 a.m. on June 12, 2006; and from 8 p.m. on July 14, 2006, until 5 a.m. on July 17, 2006, to facilitate the Outer and Inner Loop shifts of vehicular traffic for the new Woodrow Wilson Bridge construction project.
SUMMARY: Maryland and Virginia,
Coordinators for the construction of the new Woodrow Wilson Bridge Project requested a temporary deviation from the current operating regulation for the existing Woodrow Wilson Memorial (I95) Bridge set out in 33 CFR 117.255(a). The coordinators requested the temporary deviation to close the existing drawbridge to navigation to accommodate the shifting of vehicular traffic on the Outer and Inner Loops of the Capital Beltway/I95 North. The Outer and Inner Loops of the Capital Beltway/I95 North will be reduced from three lanes to only one lane between the Route 1 Interchange and the Wilson Bridge. Project traffic engineers anticipate traffic impacts to peak on Saturday afternoon, with 10 to 15 mile backups and delays of 60 to 90 minutes. Maintaining the existing drawbridge in the closedtonavigation position from 8 p.m. on Friday, June 9, 2006, through 5 a.m. on Monday, June 12, 2006 and from 8 p.m. on Friday, July 14, 2006, through 5 a.m. on Monday, July 17, 2006, will help reduce the impact to vehicular traffic during these phases of new bridge construction.
The Coast Guard has informed the known users of the waterway of the closure period for the bridge so that these vessels can arrange their transits to minimize any impact caused by the temporary deviation.
In accordance with 33 CFR 117.35(c), this work will be performed
with all due speed in order to return the bridge to normal operation as
soon as possible. This deviation from the operating regulations is authorized under 33 CFR 117.35.
Dated: April 13, 2006.
Waverly W. Gregory, Jr.,
Chief, Bridge Administration Branch, Fifth Coast Guard District. [FR Doc. 063783 Filed 42006; 8:45 am]
BILLING CODE 491015P
FOR FURTHER INFORMATION CONTACT Waverly W. Gregory, Jr., Bridge Administrator, Fifth Coast Guard District, at (757) 3986222.
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 26 CFR Part 1 40 CFR Part 180 47 CFR Part 73 50 CFR Part 17 33 CFR Part 117 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 33 CFR Part 100 40 CFR Part 63 26 CFR Part 301 50 CFR Part 622 39 CFR Part 111 40 CFR Part 300 44 CFR Part 65 50 CFR Part 660 40 CFR Part 271 40 CFR Parts 52 and 81 47 CFR Part 64 50 CFR Part 665 49 CFR Part 571 44 CFR Part 64 14 CFR Part 23 47 CFR Part 76 50 CFR Part 229