SUBJECT CATEGORY: Intent To Prepare a Draft Supplemental Environmental Impact Statement (DSEIS) for the Nourishment of 25,000 ft of Beach in Topsail Beach, Onslow County, NC
DOCUMENT SUMMARY: The U.S. Army Corps of Engineers (COE), Wilmington District, Wilmington Regulatory Field Office has received a request for Department of the Army authorization, pursuant to Section 404 of the Clean Water Act and Section 10 of the Rivers and Harbors Act, from the Town of Topsail Beach to conduct an emergency beach fill project to protect ocean front development and infrastructure until such time that a federally authorized shore protection project can be implemented. At this time, the construction date for the Federal project is uncertain. A Draft General Reevaluation ReportEnvironmental Impact Statement (GRREIS has been prepared by the U.S. Army Corps of Engineers (USACE) and was released for public review and comment in June 2006 (USACE, 2006). Given the current status of the GRREIS and the need for Congressional authorization, funding, preparation of plans and specifications, and rightofway acquisition, the Federal project may not be implemented until Fiscal Year 2010, or possibly later.
SUMMARY: Topsail Beach, Onslow County, NC; beach nourishment,
Beach Fill Surveys & Design. Typical crosssections of the beach along the Topsail Beach project area will be surveyed. Nearshore profiles will extend seaward of the monuments to a point equal to or greater than 50 feet seaward of the construction toe of fill. The total volume of beach fill to be placed in front of the existing development and infrastructure will be based on an evaluation of erosion of the project area from 2002 through the expected construction of the Federal project.
Geotechnical Investigations. The offshores and search investigations include approximately two square miles (1,220 acres) of seabed. Offshore investigations include bathymetric surveys, sidescan sonar surveys, seismic and cultural resource surveys, as well as vibracore collection and analysis. The results of the offshore investigations coupled with the compatibility of the sand resource area and native beach sand will be assessed to define the borrow area.
Environmental Resource Coordination & Permitting. The GRREIS prepared by the U.S. Army Corps of Engineers prepared an Environmental Impact Statement (EIS) for the larger Federal Shore protection project. The interim (emergency) beach fill project will be subject to Section 10 of the Rivers and Harbors Act, Section 404 of the Clean Water Act and the State Environmental Policy Act (SEPA).
Preliminary coordination with the USACEWilmington District resulted in a determination that a Department of the Army Application for an Individual Permit will be needed for project compliance with Sections 10 and 404. Similarly, coordination with the North Carolina Division of Coastal Management determined that the project would require a State EIS developed in accordance with SEPA; as well as a Major Permit under the Coastal Area Management Act.
2. Proposed Action. The scope of activities for the proposed emergency beach fill project includes: (1) Vibracores in the identified borrow area, (b) side scan sonar surveys of the ocean bottom, (c) in water investigations of potential near shore hard bottom resources identified by the side scan sonar survey, and (d) beach profile surveys. Offshore investigations include bathymetric surveys, sidescan sonar surveys, seismic and cultural resource surveys, as well as vibracore collection and analysis. The results of the offshore investigations coupled with the compatibility of the sand resource area and native beach sand will be assessed to define the borrow area.
3. Issues. There are several potential environmental issues that will be addressed in the DSEIS. Additional issues may be identified during the scoping process. Issues initially identified as potentially significant include:
a. Potential impact to marine biological resources (organisms, passageway for fish and other marine life) and Essential Fish Habitat, particularly Hard Bottoms.
b. Potential impact to threatened and endangered marine mammals, birds, fish, and plants.
c. Potential impacts to water quality.
d. Potential increase in erosion rates to adjacent beaches.
e. Potential impacts to navigation, commercial and recreational.
f. Potential impacts to private and public property.
g. Potential impacts on public health and safety.
h. Potential impacts to recreational and commercial fishing.
i. The compatibility of the material for nourishment.
j. Potential economic impacts.
4. Alternatives. Several alternatives are being considered for the proposed
[[Page 75512]]
project. These alternatives will be further formulated and developed
during the scoping process and an appropriate range of alternatives,
including the no action alternative, will be considered in the Supplemental Draft EIS.
5. Scoping Process. A public scoping meeting (see DATES) will be held to receive public comment and assess public concerns regarding the appropriate scope and preparation of the DSEIS. Participation in the public meeting by Federal, State, and local agencies and other interested organizations and persons is encouraged.
The COE will also be consulting with the U.S. Fish and Wildlife Service under the Endangered Species Act and the Fish and Wildlife Coordination Act, and with the National Marine Fisheries Service under the MagnusonStevens Act and Endangered Species Act. Additionally, the EIS will assess the potential water quality impacts pursuant to Section 401 of the Clean Water Act, and will be coordinated with the North Carolina Division of Coastal Management (DCM) to determine the projects consistency with the Coastal Zone Management Act. The COE will closely work with DCM through the EIS to ensure the process complies with all State Environmental Policy Act (SEPA) requirements. It is the COE and DCM's intentions to consolidate both NEPA and SEPA processes to eliminate duplications.
6. Availability of the Draft Supplemental EIS. The DSEIS is expected to be published and circulated sometime in early 2007, and a public hearing will be held after the publication of the DSEIS.
Dated: December 4, 2006.
John E. Pulliam, Jr.
Colonel, U.S. Army, District Commander.
[FR Doc. 069727 Filed 121406; 8:45 am]
BILLING CODE 3710GNM
FOR FURTHER INFORMATION CONTACT Questions about the proposed action and DSEIS can be directed to Mr. Dave Timpy, Wilmington Regulatory Field Office, telephone: (910) 2514634.
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 47 CFR Part 73 26 CFR Part 1 40 CFR Part 180 33 CFR Part 117 50 CFR Part 17 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 40 CFR Part 63 33 CFR Part 100 50 CFR Part 622 50 CFR Part 660 26 CFR Part 301 44 CFR Part 65 39 CFR Part 111 40 CFR Part 300 6 CFR Part 5 40 CFR Part 271 47 CFR Part 64 40 CFR Parts 52 and 81 50 CFR Part 665 10 CFR Part 50 44 CFR Part 64 49 CFR Part 571 39 CFR Part 3020