SUBJECT CATEGORY: Basin Electric Power Cooperative, Inc.; Notice of Intent To Hold Public Scoping Meeting and Prepare an Environmental Assessment
DOCUMENT SUMMARY: The Rural Utilities Service (RUS) an Agency delivering the U.S. Department of Agriculture's Rural Development Utilities Programs, hereinafter referred to as Rural Development and/or Agency, intends to hold a public scoping meeting and prepare an Environmental Assessment (EA) in connection with possible impacts related to a project being proposed by Basin Electric Power Cooperative, Inc. (Basin Electric), of Bismarck, North Dakota. The proposal consists of the construction and operation of a natural gasfired combustion turbine generation facility referred to as the Culbertson Unit 1 East Side Peaking Project, consisting of a single maximum net 100 Megawatt (MW) unit, at a site near Culbertson, Montana.
SUMMARY: Basin Electric Power Cooperative, Inc.; Public Scoping Meeting and Environmental Assessment,
Alternatives to be considered by RUS include no action, purchased power, load management, renewable energy sources, distributed generation, and alternative site locations. Comments regarding the proposed project may be submitted (orally or in writing) at the public scoping meeting or in writing within 30 days after the February 26, 2008, scoping meeting to RUS at the address provided in this notice.
A proposal development documentAlternative Evaluation and Site Selection Studyis available for public review at RUS or Basin Electric, at the addresses provided in this notice. This study is also available at the Culbertson Public Library, 202 Broadway, Culbertson, MT 59218.
From information provided in the study mentioned above, and using input provided by government agencies, private organizations, and the public, RUS will prepare a Draft EA. The Draft EA will be available for review and comment for 45 days after distribution. A Final EA will then be prepared that considers all comments received. The Final EA will be available for review and comment for 30 days after distribution. Following the 30day comment period, RUS will prepare either a Finding of No Significant Impact (FONSI) or an Environmental Impact Statement (EIS). Notices announcing the availability of the Draft and Final EA and a FONSI, as appropriate, will be published in the Federal Register and in local newspapers.
Any final action by RUS related to the proposed projects will be
subject to, and contingent upon, compliance with all relevant Federal, State and local
[[Page 6921]]
environmental laws and regulations and completion of the environmental
review requirements as prescribed in the RUS Environmental Policies and Procedures (7 CFR Part 1794).
Dated: January 31, 2008.
James R. Newby,
Assistant Administrator, Electric Programs.
[FR Doc. E82101 Filed 2508; 8:45 am]
BILLING CODE 341015P
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 47 CFR Part 73 26 CFR Part 1 40 CFR Part 180 33 CFR Part 117 50 CFR Part 17 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 40 CFR Part 63 33 CFR Part 100 50 CFR Part 622 50 CFR Part 660 26 CFR Part 301 44 CFR Part 65 39 CFR Part 111 40 CFR Part 300 6 CFR Part 5 40 CFR Part 271 47 CFR Part 64 40 CFR Parts 52 and 81 50 CFR Part 665 10 CFR Part 50 44 CFR Part 64 49 CFR Part 571 39 CFR Part 3020