Browse: Departments Dates Agencies
USC ID: [USCG-2008-0228]
SUBJECT CATEGORY: Drawbridge Operation Regulations; Norwalk River, Norwalk, CT
DOCUMENT SUMMARY: The Commander, First Coast Guard District, has issued a temporary deviation from the regulations governing the operation of the Washington Street S136 Bridge, across the Norwalk River, mile 0.0, at Norwalk, Connecticut. While in effect, this deviation allows the bridge owner to open only one of the two moveable spans for bridge openings. Vessels that require a full twospan bridge opening will be required to provide at least a twelvehour advance notice by calling the bridge operator. This deviation is necessary to facilitate scheduled bridge maintenance.
SUMMARY: Norwalk River, Norwalk, CT,
The owner of the bridge, Connecticut Department of Transportation, requested a temporary deviation to facilitate scheduled structural maintenance and painting at the bridge.
In order to perform the structural and bridge painting operations, one of the two moveable spans must remain in the closed position in order to erect paint containment and perform the required bridge maintenance.
We issued a temporary deviation (USCG20070185; 73 FR 1273, Jan. 8, 2008) authorizing single leaf operation for bridge painting effective from January 2, 2008 through March 31, 2008. On March 13, 2008, the bridge owner requested that the single leaf operation for bridge painting continue through the end of April 2008, to allow completion of this project.
Under this second temporary deviation the Washington Street S136 Bridge across the Norwalk River, mile 0.0, at Norwalk, Connecticut, need open only one of the two moveable spans for bridge openings from April 1, 2008 through April 30, 2008. Vessels requiring a full twospan bridge opening may do so provided that they give at least a twelvehour advance notice to the bridge operator by calling (203) 8667691.
Should the bridge maintenance authorized by this temporary deviation be completed before the end of the effective period published in this notice, the Coast Guard will rescind the remainder of this temporary deviation, and the bridge shall be returned to its normal operating schedule. Notice of the above action shall be provided to the public in the Local Notice to Mariners and the Federal Register, where practicable.
In accordance with 33 CFR 117.35(e), the bridge must return to its
regular operating schedule immediately at the end of the designated
time period. This deviation from the operating regulations is authorized under 33 CFR 117.35.
Dated: April 1, 2008.
Gary Kassof,
Bridge Program Manager, First Coast Guard District.
[FR Doc. E87675 Filed 41008; 8:45 am]
BILLING CODE 491015P
FOR FURTHER INFORMATION CONTACT Judy Leung-Yee, Project Officer, First Coast Guard District, at (212) 6687165.
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 26 CFR Part 1 40 CFR Part 180 47 CFR Part 73 50 CFR Part 17 33 CFR Part 117 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 33 CFR Part 100 40 CFR Part 63 50 CFR Part 622 26 CFR Part 301 39 CFR Part 111 40 CFR Part 300 50 CFR Part 660 44 CFR Part 65 40 CFR Parts 52 and 81 40 CFR Part 271 47 CFR Part 64 50 CFR Part 665 47 CFR Part 76 50 CFR Part 229 14 CFR Part 23 14 CFR Part 25 21 CFR Part 522