SUBJECT CATEGORY: Notice of Intent To Prepare a Draft Environmental Impact Statement for Carolinas Cement Company LLC Castle Hayne Project in New Hanover County, NC
DOCUMENT SUMMARY: The U.S. Army Corps of Engineers (COE), Wilmington District, Wilmington Regulatory Division has received a request for Department of the Army authorization, pursuant to Section 404 of the Clean Water Act and Section 10 of the Rivers and Harbors Act, from Carolinas Cement Company LLC (a subsidiary of Titan America LLC) to construct the Carolinas Cement Company LLC Castle Hayne Project. This project will include quarrying to support cement manufacturing in northern New Hanover County, NC.
The proposed project will require the excavation of an open pit adjacent to the Northeast Cape Fear River in order to extract and process the raw materials (calcium carbonate and limestone) in order to produce Portland Cement.
Existing infrastructure including railroad, interstate highway, and waterways allow for both the shipment of product from the plant and the receipt of materials, such as coal. The Castle Hayne site is the location of former cement manufacturing facility and an unrelated, active aggregate quarry.
SUMMARY: Carolinas Cement Company LLC Castle Hayne Project; New Hanover County, NC,
The Carolinas Cement Company has provided the following information about the purpose of the proposed project:
The purpose of the proposed project is to establish a quarry from which it can extract marl and limestone that will support manufacturing Portland cement to supply the eastern North Carolina market in an economically viable fashion. To be economically viable the minable resource must be within a 3 mile radius of the manufacturing facility and must provide for a longterm, at least 30 years, marl and limestone resource of sufficient quality that can be recovered in a systematic and costeffective manner. Based on the economies of scale and the projected market demand, the proposed plant will have a capacity of 2.3 million short tons per year of finished Portland cement. Furthermore, the manufacturing facility must be accessible to suitable modes of transportation. The relative cost of transporting a ton of Portland cement increases from barge to rail to trucks. Titan America's Roanoke Cement Company facility currently moves 50% of the Portland cement it produces by rail in the midAtlantic region. The cost of establishing and operating a Portland cement quarrying/manufacturing operation is substantial. The Portland cement market is cyclical depending upon the growth and contraction of the construction industry. It is important to locate a Portland cement operation where quarrying, manufacturing, and transportation costs and logistics allow for longterm production in an economical and efficient manner. The magnitude of the necessary investment in property and personnel requires the Portland cement industry to develop production plans based on longterm horizons. Since 1950, no manufacturing facility of the size proposed has commenced operations without 40 to 50 years of reserves, and currently operating Portland cement plants have been operating an average of 44 years. Based on this, the applicant requires at least a 30year resource reserve to construct the proposed facility.
The primary considerations in economic Portland cement production include raw materials to provide the necessary chemistry, availability of other materials (often byproducts from other industries), and transportation and power infrastructure, near to the markets that the plant is intended to serve. These primary considerations are interrelated.
Proposed Impacts to Wetlands and Surface Waters: Surface waters and wetlands have been delineated for the proposed project site. Field reviews of the delineations with the U.S. Army Corps of Engineers (USACE), and North Carolina Division of Water Quality (DWQ) have been conducted with final USACE verification of the wetlands delineation pending. The North Carolina Division of Coastal Management's (NCDCM) Coastal Area Management Act (CAMA) jurisdictional Areas of Environmental Concern (AECs) have also been identified for the site. Field reviews of the CAMA regulated AEC boundary have been conducted and agreed to by the NCDCM. The proposed quarrying action will impact approximately 493 acres of wetlands. This total includes approximately 214 acres of wetlands located within CAMA jurisdictional areas.
Scope of Investigations: Based upon the proposed impacts to wetlands and surface waters, Carolinas Cement Company LLC has been advised by the U.S. Army Corps of Engineers that an Environmental Impact Statement (EIS) will be required for the proposed Project. The scope of the EIS investigation will include the following: Alternatives analyses, Affected environment, Environmental consequences, Secondary and cumulative environmental impacts, and Mitigation.
Alternatives analyses: Council on Environmental Quality (CEQ)
regulations (40 CFR 1502.14(a)) require an environmental impact
statement (EIS) to ``rigorously explore and objectively evaluate all
reasonable alternatives'' for a proposed action. The regulations (40
CFR 1502.14(b)) further require that substantial treatment be made of
each alternative considered in detail, including the proposed action.
The Proposed Project and a reasonable number of alternatives, including
the no action alternative and quarrying for marl in other areas within
and outside of New Hanover County and/or eastern North Carolina, will be evaluated and compared in the EIS. The factors used
[[Page 31073]]
to compare the alternatives will be the same for each of the alternatives.
Affected environment: CEQ regulations (40 CFR 1502.15) require the EIS to describe the environment of the areas to be affected or created by the alternatives under consideration. The data and analysis shall be commensurate with the importance of the impact. Based upon preliminary evaluation of the proposed Project, it appears the primary areas of environmental concern will focus on the loss of wetland and other aquatic resource functions and values including impacts to wetlands within designated AEC's, mitigation of such losses, and the effect of the proposed quarry on groundwater and surface water quality.
In preparation for the EIS, the following studies have been completed or are ongoing for the proposed Project:
Environmental consequences: CEQ regulations (40 CFR 1502.16) state the EIS will include the environmental impacts of the alternatives including the proposed action, any adverse environmental effects which cannot be avoided should the proposal be implemented, the relationship between shortterm uses of man's environment and the maintenance and enhancement of longterm productivity, and any irreversible or irretrievable commitments of resources which would be involved in the proposal should it be implemented. The EIS will identify and disclose the direct impacts of the proposed project and study a reasonable number of alternatives on the following: Topography, geology, soils, climate, biotic communities, wetlands, fish and wildlife resources, endangered and threatened species, hydrology, water resources and water quality, floodplains, CAMA jurisdictional areas, hazardous materials, air quality, noise, aesthetics, recreational resources, historical and cultural resources, socioeconomics, land use, public health and safety, energy requirements and conservation, natural or depletable resources, drinking waters, and environmental justice.
Secondary and cumulative environmental impacts: Cumulative impacts result from the incremental impact of the proposed action when added to past, present, and reasonably foreseeable future actions, regardless of what agency or person undertakes the action. GIS data and mapping will be used to evaluate and quantify secondary and cumulative impacts of the proposed Project with particular emphasis given to wetlands and surface/groundwater resources.
Mitigation: CEQ regulations (40 CFR 1502.14, 1502.16, and 1508.20) require the EIS to include appropriate mitigation measures. The USACE has adopted, through the CEQ), a mitigation policy which embraces the concepts of ``no net loss of wetlands'' and project sequencing. The purpose of this policy is to restore and maintain the chemical, biological, and physical integrity of ``Waters of the United States,'' specifically wetlands. Mitigation of wetland impacts has been defined by the CEQ to include: avoidance of impacts (to wetlands), minimizing impacts, rectifying impacts, reducing impacts over time, and compensating for impacts (40 CFR 1508.20). Each of these aspects (avoidance, minimization, and compensatory mitigation) must be considered in sequential order. As part of the EIS, the applicant will develop a compensatory mitigation plan detailing the methodology and approach to compensate for unavoidable impacts to waters of the U.S. including wetlands.
NEPA/SEPA Preparation and Permitting: Because the proposed Castle Hayne quarry project requires approvals from federal and state agencies under both the National Environmental Policy Act (NEPA) and the State Environmental Policy Act (SEPA), a joint Federal and State Environmental Impact Statement (EIS) will be prepared. The U.S. Army Corps of Engineers will serve as the lead agency for the process. The EIS will be the NEPA document for the Corps of Engineers (404 permit) and the SEPA document for the State of North Carolina (CAMA permit).
Based on the size, complexity, and potential impacts of the
proposed project, the Applicant has been advised by the U.S. Army Corps
of Engineers to identify and disclose the environmental impacts of the
proposed project in an Environmental Impact Statement (EIS). Within the
EIS, the Applicant will conduct a thorough environmental review,
including an evaluation of a reasonable number of alternatives. After
distribution and review of the Draft EIS and Final EIS, the Applicant
understands that the U.S. Army Corps of Engineers will issue a Record
of Decision (ROD) for the project. The ROD will document the completion
of the EIS process and will serve as a basis for permitting decisions by federal and state agencies.
Christine M. Brayman,
Deputy District Engineer, Programs and Project Management.
[FR Doc. E812065 Filed 52908; 8:45 am]
BILLING CODE 3710GNP
FOR FURTHER INFORMATION CONTACT Questions about the proposed action and DEIS can be directed to Mr. Henry Wicker, Regulatory Division, telephone: (910) 2514930.
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 26 CFR Part 1 40 CFR Part 180 47 CFR Part 73 50 CFR Part 17 33 CFR Part 117 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 33 CFR Part 100 40 CFR Part 63 50 CFR Part 622 26 CFR Part 301 39 CFR Part 111 40 CFR Part 300 50 CFR Part 660 44 CFR Part 65 40 CFR Parts 52 and 81 40 CFR Part 271 47 CFR Part 64 50 CFR Part 665 47 CFR Part 76 50 CFR Part 229 14 CFR Part 23 14 CFR Part 25 21 CFR Part 522