DEPARTMENT OF DEFENSE
Engineers Corps
NOTICE: NOTICES
ACTION: Intent to Prepare a Draft Environmental Impact Statement; Clear Creek General Reevaluation Study:
DOCUMENT ACTION: Notice of intent.
SUBJECT CATEGORY: Intent To Prepare a Draft Environmental Impact Statement for the Clear Creek General Reevaluation Study, Brazoria, Fort Bend, Galveston and Harris Counties, TX
DOCUMENT SUMMARY: The Clear Creek watershed drains portions of Fort Bend,
Harris, Galveston, and Brazoria counties, Texas, including portions of
Houston and the smaller towns of League City, Friendswood and Pearland,
among others. The watershed also forms part of the boundary between
Harris County to the north and Galveston and Brazoria counties to the
south. Clear Creek flows into the west side of upper Galveston Bay
through Clear Lake. The Draft Environmental Impact Statement (DEIS)
will evaluate several flood detention and conveyance features to reduce
flooding of homes and businesses in the Clear Creek Watershed. The
study will focus on environmental and social conditions currently
present and those likely to be affected by the proposed changes in the
watershed. The floodcontrol project includes construction of several
miles of high flow channel adjacent to the existing channel, while
preserving the existing channel and floodplain forest. Detention of
flood waters would also be provided in some areas where the high flow
channel diverges from the low flow channel and in offline detention
areas adjacent to the creek. All flood control measures on Clear Creek
occur upstream of the Dixie Farm Road crossing. The proposed project
also includes widening three tributaries to Clear Creek, Mud Gully,
Turkey Creek, and Mary's Creek, for improved conveyance of flood flows,
with detention basins constructed adjacent to Mary's Creek and between
Clear Creek and Mud Gully.
SUMMARY: Brazoria, Fort Bend, Galveston and Harris Counties, TX.,
SUPPLEMENTAL INFORMATION
(1) Background. Flooding along Clear Creek has caused problems for over 30
[[Page 35672]]
years. Floodwaters in 1973, 1976, 1979, 1989, and 1994 substantially
damaged residences along the creek. Heavy rains from Tropical Storm
Allison in 2001 resulted in severe flooding along Clear Creek and
prompted the buyout of approximately 300 floodprone homes. However,
flooding is not only a problem associated severe rain events, but has
become increasingly more frequent along Clear Creek, even with moderate
amounts of rainfall. Local authorities have made limited channel
improvements to address specific flood concerns, but those efforts have
contributed little to resolving the current largescale flooding
problem. The Clear Creek Federal flood control project was authorized
by Congress in the Flood Control Act of 1968 (Pub. L. 91611, Section
221). The authorized project extended 31 miles from Clear Lake to the
Fort Bend County line. Plans included deepening, widening, and
realigning the creek channel. The congressional authorization for this
project only allows the consideration of reducing flood damage caused
by rainfall runoff along the main channel of Clear Creek and not
coastal flooding caused by tropical storm systems. In 1982 the Phase I
General Design Memorandum, including the Final Environmental Impact
Statement, was signed by the U.S. Army Corps of Engineers (USACE)
Southwest Division Engineer, thus authorizing the detailed design. Due
to concerns regarding its design, the project's nonFederal sponsors,
Galveston County and Harris County Flood Control District, with input
from the public and governmental entities, requested reevaluation of
the design. In 1997, the sponsors requested the USACE adopt changes to
the plans. The changes requested by the nonFederal sponsors were
beyond the discretionary authority of the USACE Southwest Division
Commander to approve. As a result, in February 1999, the USACE decided
a general reevaluation study would be needed. In April 1999, the non
Federal sponsors agreed to accept the USACE recommendation to conduct
the general reevaluation study. The general reevaluation study
reconsidered the previously authorized project as well as nonFederal
sponsorproposed alternatives and other alternatives that were deemed
reasonable. Brazoria County Drainage District
4 joined the nonFederal sponsors in this effort by June 1999.
(2) Alternatives. The construction alternatives that will be
evaluated are: (1) Constructing 15.2 miles of 130 ft to 240 ft wide
high flow channel in two separate sections of Clear Creek. (2)
Detention of 485 acre feet of flood water in the high flow channel of
Clear Creek where it diverges from the low flow channel. (3) Detention
of 1,750 acre feet of flood water in a 160 acre basin adjacent to Clear
Creek. (4) Construction of a grasslined channel on 2.4 miles of Turkey
Creek to its confluence with Clear Creek. (5) Construction of a
concretelined channel for 0.8 mile of Mud Gully in the reach which is
located between the northbound and southbound lanes of Beamer Rd. (6)
Detention of 1,515 acre feet of flood water in a 120 acre basin between
Clear Creek and Mud Gully. (7) Construction of a 2.1 mile grasslined
channel on Mary's Creek. (8) Detention of 857 acre feet of flood water
in two detention basins totaling 120 acres along Mary's Creek.
(3) Scoping. Scoping meetings were held on March 15, 2001 at the
Friendswood High School in Friendswood, TX, on March 15, 2001 in
Friendswood, TX, on May 3, 2001 in League City, TX, and on May 9, 2001
in Pearland, TX. The scoping process involved Federal, State and local
agencies, and other interested persons and organizations. Comments were
received for 30 days following each scoping meeting. Comments will be
considered during preparation of the EIS. At this time, there are no plans for an additional scoping effort.
(4) Coordination. Further coordination with environmental agencies
will be conducted under the National Environmental Policy Act, the Fish
and Wildlife Coordination Act, the Endangered Species Act, the Clean
Water Act, the Clean Air Act, the National Historic Preservation Act,
the MagnusonStevens Fishery Conservation and Management Act (Essential
Fish Habitat), and the Coastal Zone Management Act under the Texas Coastal Management Program.
(5) DEIS Preparation. It is estimated that the DEIS will be
available to the public for review and comment in March 2009. Richard Medina,
Chief, Planning and Environmental Branch.
[FR Doc. E814239 Filed 62308; 8:45 am]
BILLING CODE 371052P
FOR FURTHER INFORMATION CONTACT Mr. Robert Heinly, (409) 766-3992,
Planning Lead, Planning Section, Planning, Environmental and Regulatory
Division; or Ms. Andrea Catanzaro, (409) 7666346, Environmental Lead,
Environmental Section, Planning, Environmental and Regulatory Division.