SUBJECT CATEGORY: Kaibab National Forest; AZ; Uranium Exploratory Drilling Project
DOCUMENT SUMMARY: The USDA Forest Service is preparing an Environmental Impact Statement (EIS) to consider and disclose the effects of proposed exploratory drilling for uranium on National Forest System (NFS) land. The proposed exploratory drilling project would occur on mining claims held by VANE Minerals, Inc. and Uranium One (with all exploratory drilling to be completed by VANE Minerals, Inc.) in the Tusayan Ranger District, Kaibab National Forest within Townships 27, 28, 29 and 30 North, Ranges 2, 3, 4 and 5 East, Gila and Salt River Meridian, Coconino County, Arizona. Exploration is proposed by VANE Minerals, Inc. to determine whether uranium deposits exist on these mining claims. A total of 25 drill sites are planned by VANE Minerals, Inc. Shallow drill holes would be drilled to determine whether or not ``breccia pipes'' occur at the site. Breccia pipes are the geologic formations found in the Colorado Plateau region that can contain uranium minerals. Deep drill holes would be drilled to confirm the presence and extent of the breccia pipes and to gather additional information regarding the uranium concentrations found in these pipes. This EIS will include analyses and will disclose the potential environmental effects for future exploratory uranium drilling and accompanying grounddisturbing activities at the seven sites that were part of the VANE project challenged in Center for Biological Diversity v. Stahn, Civ. No. 088031PCTMHM (D. Ariz.).
SUMMARY: Kaibab National Forest; AZ; Uranium Exploratory Drilling Project,
In 2006, VANE Minerals, Inc. submitted a Plan of Operations to the Forest Service to drill exploration holes for uranium at a total of (10) sites within the Tusayan Ranger District, Kaibab National Forest. A categorical exclusion from documentation under the National Environmental Protection Act (NEPA) was completed in December 2007, and the Forest Service approved VANE Minerals, Inc.'s plan to drill on seven (7) of the ten (10) sites, in areas accessible by Forest Service roads. Exploratory drill operations began in March 2008, and one site was completed.
A lawsuit was filed against the agency's use of a categorical exclusion and a Preliminary Injunction (PI) was ordered on further uranium exploratory drilling. The original agency decision has been withdrawn and an environmental impact statement will be completed on the balance of the original ten (10) sites (one site had exploratory drilling on it and was rehabilitated before the PI was instituted by the court), plus additional proposed sites VANE Minerals, Inc. submitted to the Forest Service in 2007.
The agency's purpose is to analyze the proposals from VANE Minerals, Inc. and any reasonable alternatives, including any mitigation measures to protect the surface resources in the areas of exploratory drilling in order to approve a plan of operations for exploration. The agency's need for action is based on statutes and policy that govern mining on NFS land.
Most NFS land is subject to the location of certain minerals under
the Mining Law of 1872, as amended (30 U.S.C. 2154, et seq.), and the
directives in Forest Service Manual 2800. Prospecting, locating and
developing the mineral resources on NFS land are also subject to other
rules and regulations. These include, but are not limited to, the 1897
Organic Administration Act, the 1960 MultipleUse SustainedYield Act,
the 1970 Mining and Minerals Policy Act, and Regulations at Title 36,
Code of Federal Regulations, part 228A which sets forth rules and
procedures governing the use of NFS lands in conjunction with [[Page 60234]]
operations authorized by general mining laws.
The Forest Service proposes to authorize VANE Minerals, Inc. to perform exploratory drilling at the 25 drill sites proposed. This Proposed Action would constitute exploratory drilling only. No mining extraction or transporting of uranium minerals for processing would be contemplated or permitted by this proposal.
This notice of intent initiates the scoping process which guides the development of the environmental impact statement. The Forest received several comments during the categorical exclusion analysis in 2007 which will be considered in this analysis. The Forest Service encourages the public to express issues, concerns, and suggestions they may have about this proposed action. Comments should be directly related to issues associated with the proposed action, rather than general advocacy of or opposition to the project, to best assist us in the NEPA analysis. Although comments are welcome at any time during this NEPA analysis, they will be most useful to us if they are received within 30 days following the publication of this notice.
The Forest Supervisor for the Kaibab National Forest of the Southwestern Region of the USDA Forest Service is the Responsible Official.
The decision to be made is what plan of operations to approve for
exploration, including any requirements for surface resource
protection. VANE Minerals, Inc. has a statutory right to explore for locatable minerals under the 1872 Mining Law.
Early Notice of Importance of Public Participation in Subsequent Environmental Review
A draft environmental impact statement will be prepared for comment. The comment period on the draft environmental impact statement will be 45 days from the date the Environmental Protection Agency publishes the notice of availability in the Federal Register. The Forest Service believes, at this early state, it is important to give reviewers notice of several court rulings related to public participation in the environmental review process. First reviewers of draft environmental impact statements must structure their participation in the environmental review of the proposal so that it is meaningful and alerts an agency to the reviewer's position and contentions. Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519, 553 (1978). Also, environmental objections that could be raised at the draft environmental impact statement stage but that are not raised until after the completion of the final environmental impact statement may be waived or dismissed by the courts. City of Angoon v. Hodel, 803 F.2d 1016, 1022 (9th Cir. 1986) and Wisconsin Heritages, Inc. v. Harris, 490 F. Supp. 1334, 1338 (E.D. Wis. 1980). Because of these court rulings, it is very important that those interested in this proposed action participate by the close of the 45day comment period so that substantive comments and objections are made available to the Forest Service at a time when it can meaningfully consider them and respond to them in the final environmental impact statement.
To assist the Forest Service in identifying and considering issues and concerns on the proposed action, comments on the draft environmental impact statement should be as specific as possible. It is also helpful if comments refer to specific pages or chapters of the draft statement. Comments may also address the adequacy of the draft environmental impact statement or the merits of the alternatives formulated and discussed in the statement. Reviewers may wish to refer to the Council on Environmental Quality Regulations for implementing the procedural provisions of the National Environmental Policy Act at 40 CFR 1503.3 in addressing these points.
Comments received, including the names and addresses of those who
comment, will be considered part of the public record on this proposal and will be available for public inspection.
(Authority: 40 CFR 1501.7 and 1508.22; Forest Service Handbook 1909.15, Section 21).
Dated: October 2, 2008.
Michael P. Williams,
Forest Supervisor.
[FR Doc. E823993 Filed 10908; 8:45 am]
BILLING CODE 341011M
FOR FURTHER INFORMATION CONTACT For further information on the VANE Minerals Uranium Exploratory Drilling Project (Project), please contact Tom Mutz, Lands and Minerals Staff Officer, in writing at Williams and Tusayan Ranger Districts, 742 S. Clover Rd., Williams AZ 86046 or by telephone at (928) 6355600. Questions regarding the Forest Service NEPA process may be directed to Alvin Brown, Forest NEPA Coordinator, at 800 S. 6th St., Williams, AZ 86046 and telephone (928) 6358200.
14 CFR Part 39 40 CFR Part 52 14 CFR Part 71 33 CFR Part 165 50 CFR Part 679 47 CFR Part 73 26 CFR Part 1 40 CFR Part 180 33 CFR Part 117 50 CFR Part 17 44 CFR Part 67 50 CFR Part 648 14 CFR Part 97 40 CFR Part 63 33 CFR Part 100 50 CFR Part 622 50 CFR Part 660 44 CFR Part 65 26 CFR Part 301 39 CFR Part 111 40 CFR Part 300 6 CFR Part 5 40 CFR Part 271 47 CFR Part 64 40 CFR Parts 52 and 81 50 CFR Part 665 10 CFR Part 50 44 CFR Part 64 49 CFR Part 571 39 CFR Part 3020